Contractual Interpretation - What the Law Says
- Sep 15, 2023
Head Contractor WDR excludes Subcontractor Time-related Costs
- Mar 3, 2023
'Project Specific' Overhead Recovery
- Oct 5, 2022
One Notice Will Do, for “Extension of Time Variations” NZS3910
- Apr 10, 2022
Getting to the Entitlement Point, is what really Matters
- Dec 12, 2021
The Engineer and Natural Justice
- Nov 28, 2021
The Principles of Valuation NZS3910:2013
- Nov 21, 2021
Subcontractor Extension of Time Dis-entitlement, No harm no foul
- Nov 14, 2021
Show me your contract
- Oct 24, 2021
Is a Bonus, Profit or Liquidated damages?
- Aug 15, 2021
Defining FF&E for New Zealand Building Contracts
- Jul 22, 2021
NZS3910:2013 The Search for Variations - a quick reference guide
- Jun 9, 2021
NZ Contractual Interpretation Case Law Development - L&M Coal v Bathurst
- Apr 21, 2021
Offsite Overhead Recovery Mission
- Mar 24, 2021
A Contract in Context, Means more than mere words can express...
- Mar 12, 2021
Detailed Design Disruption Claims
- May 9, 2020
Time to break out a “Time related overheads” claim, NZS3910 Style.
- May 2, 2020
"Let the Profit Margin be" - The Principles of Valuation
- Apr 4, 2020
Your Construction Contract [NZS3910] & the Covid-19 Shutdown
- Oct 8, 2019
When contractual interpretation isn’t what you want it to be